DEFINITE STUDY: LA VIÑA - MOTUPE - PAMPA PAÑALA 60 kV TRANSMISSION LINE AND SUBSTATIONS

  • La Viña – Motupe – Pampa Pañala 60 kV Transmission Line, 52 km, single circuit, AAAC 240 mm2 conductor, OPGW optical fiber earth wire, stell towers.
  • La Viña 60kV substation: Expansión of one line bay.
  • Motupe new substation: 60/22,9/10 kV, 16/20 MVA (ONAN/ONAF).
  • Pampa Pañala new substation: 60/22,9/10 kV, 16/20 MVA (ONAN/ONAF)
  • Southern Chiclayo substation 220/60/22,9 kV; 55/18/37 MVA (ONAF)
  • System of Telecommunications
  • Elaboration of the file, including technical specifications and tender documents.

 

 

Contracting entity: ELECTRONORTE

Location: Lambayeque - Peru

Period: Feb. 2013 – Jan. 2014